Durham highway work will add later-November lane and ramp restrictions in Oshawa, Clarington and Pickering, according to Ontario 511 records checked Friday, November 20.
The five entries below cover different work periods from those already reported by All About Durham. They are scheduled windows, not a statement that all affected roads will be continuously closed throughout the week.
Oshawa: next Ritson–Harmony work period
On Highway 401 eastbound between Ritson Road and Harmony Road, two alternating lanes are listed for nightly construction from 8 p.m. November 22 until 5 a.m. November 28.
The matching westbound section, from Harmony Road to Ritson Road, has the same two-alternating-lane restriction and overall nightly window. These are Ontario 511 records 337318 and 337317, updated November 18 at 3:13 p.m. and 3:18 p.m. respectively.
This November 22–28 period follows the previously reported November 15–21 work. It is also distinct from the separate engineering-investigation entries at Ritson Road itself.
Clarington: Highway 418 ramp and Liberty Street lane
Daily maintenance is listed for one alternating lane of the northbound Highway 418 on-ramp at Highway 401 from November 23 at 8 a.m. until November 24 at 4 p.m. Record 337403 was updated November 17 at 10:01 a.m.
On Highway 401 eastbound at Liberty Street, one left lane is scheduled for nightly engineering investigation from November 23 at 8 p.m. until November 25 at 6 a.m. Ontario 511 describes the location as between Liberty Street and Liberty Street; that should not be expanded into an assumed closure of the whole Liberty–Highway 35/115 section. Record 337486 was updated November 19 at 1:17 p.m.
Pickering: later Brock Road off-ramp window
All lanes of the Highway 401 eastbound collector off-ramp at Brock Road are listed closed nightly from November 23 at 10 p.m. until November 28 at 5:30 a.m. Record 337328 was updated November 18 at 4:39 p.m.
That is a ramp restriction, not a closure of every eastbound highway lane. It is a later work period than the Brock Road ramp window ending November 23 that was previously reported.
Other entries in Friday’s roadwork roundup repeat previously announced work. They are not being republished as new developments here. The Durham highway work notices reviewed do not provide a confirmed signed detour. Drivers should check the live provincial service before departure and follow posted traffic controls, as schedules and lane availability can change.