Darlington SMR settlement talks will resume on December 8 after the Ontario Energy Board issued a new procedural order in the payment-amounts application involving Ontario Power Generation and DNNP LP.
The November 16 order establishes the next step in the regulatory proceeding following changes affecting the first small modular reactor and shared facilities under construction at the Darlington site in Clarington.
Conference returns after a pause
The OEB had cancelled the previously scheduled procedural steps on October 27 while the applicants assessed a change and its effect on their application. The proceeding concerns payment amounts for January 1, 2027, through December 31, 2031.
The applicants subsequently asked to return to settlement discussions to consider their impact statement and a possible amendment to the existing settlement proposal.
In a November 12 letter, counsel writing for the intervenors who signed that proposal agreed to renewed discussions. The letter identified December 8 as the earliest date available to their representatives and confirmed that the applicants could also attend.
Status letter due December 11
The board has now ordered the conference to continue on December 8 with the parties and OEB staff. Participation information will be communicated closer to the date.
OPG and DNNP LP must then file a status letter by December 11. It must indicate whether a tentative agreement has been reached or whether the parties propose continuing the discussions.
The intervenors’ letter also preserved their expectation of formal discovery on the impact statement if the renewed talks leave affected issues without a settlement.
This is a new procedural decision in the Darlington SMR settlement process, not approval of a final agreement or announcement of a replacement reactor opening date. All About Durham previously reported the project’s cost-and-schedule reassessment; the newly ordered conference and reporting deadline are separate developments.